Cassette Cassettes allow very short construction times. They are therefore
particularly suitable for subsequent installation in existing workshops and
pits. Manufacturer guarantees dimensional accuracy.
Frames Usually, in the case of new buildings, the frame is the ideal
choice. The factors time, cost and precision however are carried mainly by
the customer.
Clean Layer A layer approx. 8 cm thick with a concrete quality of
at least B15. It serves as a support for the cassette.
Levelling Tool This enables precise adjustment of the cassette during
installation. The levelling result should not exceed a tolerance of more than
± 2 mm across the entire length and breadth.
Empty Pipes For the electrical installation, as a drainage outlet and
possibly for ventilation purposes, empty pipes with a Ø of 100 mm
must provided.
Fixing Layer A roughly 30 cm high concrete layer in concrete quality
of B25.
Middle Layer In B25 quality, this concrete layer connects directly
to the floor plate.
Stone Anchors Evenly distributed, the stone anchors ensure an uniform
distribution of force across the floor plate.
Floor Plate This corresponds to the height of the hall floor. Both
the floor plate and the reinforcement are subject to static calculations.
Fitted Flooring Particularly the strength plays a decisive part in
the choice of fitted flooring. The evenly distributed vertical working load
amounts to 10 kN/m². 10 kN/m².
Cassette/Frame Depending on the length of the Ground Lift, the cassette
or frame will be delivered in one or several parts. Encased in concrete, the
mobile and fixed lifting posts and the roll covering find their place.
The installation of an In Ground Lift should be planned and
executed with the utmost care. The main steps in the installation of a cassette
or frame are explained below:
Once the pit has been dug out, a drainage pipe can be laid as necessary. In
the case of the cassette construction the granular sub-base is cemented on
top of the gravel layer.
To permit the cassette to be levelled, stay bolts are screwed into the clean
layer. The cassette, placed on top of these, can then be precisely aligned
with the help of the adjusting nuts. In the case of the frame construction,
the concrete can be introduced to the pit as the second step. First, the empty
pipes for the electrical installation should be positioned.
Now the cassette is encased in liquid concrete up to a height of approx. 30
cm. Care should be taken, with this so-called fixing layer, that the cassette
does not swim. In the case of a frame, the remaining gap is filled
with gravel to the upper edge of the pit.
For the cassette construction the empty pipes for the electrical installation
are now laid. The middle layer is made by pouring in concrete up to the lower
surface of the floor plate. For the frame construction, the stay bolts can
now be screwed into the pit and the frame can be levelled.
The last step is the construction of the floor plate and the fitted flooring.
Finally, the electrical installation work can be carried out via the empty
pipes already laid.
How many lifting posts for whom? At the start of the decision-making
phase for an in-ground truck lift one of the first questions is how many lifting
posts are needed. The following is intended to help with this decision:
The smallest variation, the 2-post Mammut, is mainly for lifting towing cabins,
trucks and busses.
Where semi-trailers or articulated busses are also lifted, a 3-post Mammut
is necessary.
The 4-post Mammut offers more of everything and is ideally suitable
thanks to 2 control panels for working on two vehicles at once in the
same lane. Due to the standard synchronisation control the full scope of performance
becomes particularly apparent when lifting a truck together with its trailer.